£2950000*
Total Cost
GIFA: 1,184m2
Rec site area: 10,327m2
26 Weeks
Construction Period
Preconstruction: 33 weeks
Construction: 26 weeks
£3215000*
Total Cost
GIFA: 1,350m2
Rec site area: 10,673m2
26 Weeks
Construction Period
Preconstruction: 33 weeks
Construction: 26 weeks
£3840000*
Total Cost
GIFA: 1,776m2
Rec site area: 14,416m2
32 Weeks
Construction Period
Preconstruction: 33 weeks
Construction: 32 weeks
£4460000*
Total Cost
GIFA: 2,166m2
Rec site area: 18,662m2
36 Weeks
Construction Period
Preconstruction: 33 weeks
Construction: 36 weeks